Mill and Fill Update

The Division of Streets, Bridges & Harbor has completed the Mill & Fill program in Districts 5 and 6 with the exception of two streets, Bowen Road and 109th that will be finished after utility work being performed there is done. Work in District 4 is 85% complete as of today.

Preparations are underway to begin the program in District 3 next week, including finalization of the streets list. The Division continues the process of determining material quantities for Districts 1 & 2.

So far in 2016, more than 3,500 tons of asphalt has been used in the Mill & Fill program.


Posted by Stacy Weber on Wednesday, July 06, 2016.