Project Overview
In 2025, the City of Toledo will resurface Laskey Rd. from Secor Rd. to Douglas Rd. We will remove and replace the top three inches of asphalt and make any other necessary repairs to the pavement.
The City of Toledo has contracted with Gerken Paving, Inc. for this project.
Happening Now
Crews will begin staging the area the week of April 21, and we anticipate construction to begin the week of April 28.
Additionally, the waterline replacement happening on Sandra Dr. will also cause a full closure of Laskey Rd. for a few days – likely April 25, 26, and 27. We hope to wrap up that work before we begin the resurfacing on Laskey Rd.
Crews intend to maintain one lane of traffic in each direction through the project. The City of Toledo has contracted with Gerken Paving, Inc. for this project.
Funding
State funding: $350,000
City of Toledo: $1.6 million
Project Outcomes
- improved pavement condition