Happening Now

Crews will begin construction on Water St. the week of April 7. The City of Toledo has contracted with Geddis Paving and Excavating, Inc.

We will begin with the watermain which will take approximately 7 weeks to complete. Following the watermain installation, we will install a new storm sewer. Around mid-July we will begin the new multi-use path. We expect the project to complete in early November 2025.

There will be access to Water St. through the duration of the project. However, there will be no street parking from 7 a.m. to 5 p.m.

Project Overview

In partnership with Metroparks, the city will reconstruct Water Street from the MLK bridge to Olive Street. We will narrow Water Street, add a multi-use path connecting the Riverwalk to an existing path on Olive Street, and widen the sidewalk on Summit from Bush to the Craig Street Bridge to accommodate cyclists.

Riverside Trail at Water Street

Funding

Metroparks: $1 million
Federal grant: $650,000
State grant: $400,000
City of Toledo: $1.95 million

$4
million

Project Outcomes

  • Pedestrian safety
  • Cyclist safety
  • New storm sewer and waterlines

Get Updates

Optional. Subscribe to text updates.

You may select multiple options from either list to receive updates. Choose the roads that would most impact your daily life.

If you would like a combined update for Major Road Construction projects, please select that option from the list below.

Optional. Subscribe to other City of Toledo updates.